Housing construction is slowing in France, and bureaucracy alone cannot explain it: with construction costs up 19% since 2019 and interest rates higher, developers are struggling above all to find the buyers needed to secure financing. Procedures and legal challenges lengthen schedules, but industry specialists identify economic conditions as the main obstacle.

The decline is substantial. Between 2019 and 2025, construction starts for multifamily housing, including residential complexes, fell by a quarter. Projects that reach completion are also taking longer. On November 16, 2026, Véronique Bédague, CEO of Nexity, France’s largest property developer, estimated that delivering a home now took five years, compared with three previously. “Decision-making is slower, the mechanisms are more complex. I think we keep adding procedure upon procedure,” she said.

In Hauts-de-Seine, a 19-home development illustrates the stretched timelines. The project, presented by Marc Gédoux, president of the housing division at FFB Grand Paris, dates to 2019; the keys were not handed over until 2026. A requirement from the state heritage architect to preserve a detached house delayed the building permit. A new application had to be submitted, approved and cleared of legal challenges. According to Gédoux, the developer faced 12 challenges to the permit.

There is, however, a distinction between processing an application and contesting an authorization. In its 2024 report on building permits, the Cour des comptes, France’s public audit institution, found that municipalities generally issued permits on time. Challenges by neighbors or the state slow construction. For developers, waiting carries a direct cost: land purchases are financed through borrowing, and financing charges keep accumulating. Delays also undermine sales as some buyers who have reserved homes eventually withdraw, Gédoux explained.

Yet a building permit does not guarantee that construction can begin. The biggest difficulty remains securing enough buyers. The 19% rise in construction costs since 2019 makes homes more expensive, while interest rates have also risen, averaging 4% in the conditions described in November 2026. Banks are consequently more cautious about financing new developments.

Henry Buzy-Cazaux, president of the Institut de Management des Services Immobiliers and a former developer, described a concrete tightening of requirements. About 20 years ago, banks might finance a project once 30% to 40% of its homes had been presold. They now commonly require 50% to 60% to limit the risk of unsold homes in a difficult economic climate.

The bottleneck therefore extends beyond accumulating paperwork. Developers must secure more buyers before obtaining financing, precisely when homes have become more expensive. Faster permits alone would not resolve that problem.