Havre-Caumartin station will close for two years from late March 2027 for work on its aging 1970s structure. The busy interchange, served by Metro lines 3 and 9 with connections to RER A and E, will be one of the main disruption points in another year of construction across the Paris region’s transportation network.
Transport operators outlined major interruptions on RER A, B and C and several Metro lines on Wednesday, November 25, 2026. The work, estimated at €4 billion, is intended to modernize the network and secure its long-term operation, bringing fresh travel difficulties in the process.
Grégoire de Lasteyrie, vice president of Île-de-France Mobilités (IDFM), the regional transportation authority, defended continuing the projects begun in 2026. The network is still midway through its heavy infrastructure work, he explained. The aim is to maintain a system capable of carrying the region’s 12.6 million residents and its many tourists.
RER B service will stop for a month during the summer between Massy-Palaiseau and Saint-Rémy-lès-Chevreuse. RER A will close between Vincennes and Joinville-le-Pont for much of August. Several sections of RER C will also shut in March, May, July and August.
On the Metro, line 6 will close completely from January 7 through 21, followed by intermittent closures in subsequent months. Line 12 will suspend service two evenings a week from January through March 2027. Several stations on lines 13 and 14 will go without service for several weeks during the summer.
To limit disruption, officials are prioritizing quieter hours and the summer period. According to de Lasteyrie, ridership falls by 40% in summer. He also plans to address use of alternative routes and communication with passengers: shifting construction to quieter periods does not remove the need to organize replacement journeys.
The program also includes a new SNCF maintenance facility in the southeast of the capital. To the north, the Soissons bridge will be replaced by a modern structure to facilitate the passage of CDG Express. That service is intended to connect Roissy-Charles de Gaulle Airport with Gare de l’Est in 20 minutes.
Some interruptions will therefore be concentrated in the quieter months. At Havre-Caumartin, however, the closure will span two full years, requiring a lasting change to passengers’ connections.