The December opening of the first section of Grand Paris Express Line 18 is “highly unlikely,” Valérie Pécresse acknowledged on Monday, November 23. Malfunctions in automation systems supplied by Alstom are still preventing the start of trial operations without passengers, which must last at least two months before service can begin.
The president of Île-de-France Mobilités (IDFM) and the Île-de-France region is demanding answers from those responsible for the project. Officially, the section linking Christ de Saclay and Massy-Palaiseau is still scheduled to open before the end of the year. But no firm replacement date has been offered.
The Société des Grands Projets (SGP) initially announced an opening in the first week of December. That schedule had already slipped because of a delayed technical handover to Keolis, the operator, and RATP, the infrastructure manager. The handover took place only on October 13, two weeks later than planned.
The operators then needed to complete two months of trial operations, a period that cannot be shortened before passengers are admitted. Yet that phase “still hasn’t started,” Pécresse said on Monday, almost a month and a half after its scheduled start. The delay is therefore more than an outstanding handover formality: an entire mandatory testing period remains ahead.
The problems mainly affect the supervision and monitoring functions of Alstom’s automation systems. On Friday, RATP Chief Executive Xavier Piechaczyk explained that those systems must send the control center reliable, complete information about the condition of the infrastructure. “The system works well overall, but some malfunctions remain,” he said.
Pécresse said the situation had “gone on far too long.” The Les Républicains politician wants to convene everyone involved to obtain answers. “Alstom must find solutions to make its software reliable,” she demanded. For now, that demand comes without a new opening schedule.
Line 18 adds to the difficulties surrounding the opening of the first sections of the Grand Paris Express, which comprises 200 kilometers of new lines. Line 15 South, the first section of the orbital route intended to encircle Paris, is now expected in fall 2027. The first sections of Lines 16 and 17 have been postponed to 2028.
Those three lines share an automatic operating system different from the one used on Line 18. Delays are accumulating across the network, but they do not all involve the same equipment.