An administrative court on Friday suspended the building permit for Nantes’s planned administrative detention center, where construction began in September. Ruling on an emergency application from associations opposing the project, the judge found that an environmental impact assessment should have been conducted beforehand.
The center is part of the government’s drive to double administrative detention capacity. In Nantes, construction has met strong local opposition and prompted several demonstrations. On October 10, about 2,000 people gathered near the construction site, close to the city’s jail.
The Ligue des droits de l’Homme and nine other organizations, including Cimade, which defends refugees and migrants, have filed legal challenges seeking to overturn the project, its building permit and its environmental authorization. The prefecture, meanwhile, has designated the project as being “in the public interest.”
Suspending the permit does not permanently cancel it: the organizations pursued the emergency proceedings alongside their challenges on the merits. For now, the absence of a prior environmental assessment has led the judge to suspend the permit, while the request to overturn the project remains to be decided.